So that’s the foundations finished. Just got to fill them with this mountain of hardcore now. Thank goodness for JCBs otherwise we would be here til Christmas. We have to get a move on. Just got the hardcore to put in, a layer of sand, the damp-proof course, 1500mm of floor insulation, the reinforced mesh, underfloor heating pipes, ducting for the kitchen island and and pipework for the bath and shower then the concrete floor next week ready for the kit to be delivered a week on Monday. It feels as though we are actually getting a move on now.
Monthly Archives: September 2014
the end is nigh!!! 11 courses done, 2 to go then we will have foundations.
Who would have thought it, we are getting excited about a few thousand building blocks, but the end is in sight. We get the first lorry load of crushed concrete tomorrow. By the end of next week we will have a concrete floor, (hopefully!). All we need now is Scotframe to pull their fingers out and deliver the house kit.
The Building Site Elves have been at it again
Before
During
After The building site elves were out last night. When Brian the builder left the site there were pallet-loads of bricks strewn everywhere. When he gets there this morning they will all have been stacked strategically for him to re-start building straight away. We stacked 450 blocks last night as well as leveling sections of the sand & gravel floor to the inside of the foundations. It is beginning to look good. A pity it will all be buried out of sight!